Ranford Pool Project Update

Published on Saturday, 1 February 2025 at 12:00:00 AM

Exciting progress is being made at Ranford Pool. The car parking modifications are now complete, increasing the number of car bays. A new seasonal fire pit has been installed, which will remain locked during the prohibited burning season. Concrete pads are in place, ready for the installation of shelters, which will be completed in February. CCTV will also be installed in February to enhance security for all visitors.